Emergency Power Supply System
- Total Cost: $20.5 million
- New: 25,000 SF
- Owner: Providence Alaska Medical Center
ATS Replacements & Power Distribution Upgrades
- Total Cost: $6.5 million
- Hospital Wide Upgrades
- Owner: Providence Alaska Medical Center
PAMC Tower M “Generations”
- Total Cost: $157 million
- SF: 84,500
- Third Party Commissioning Authority Services (225,000 SF)
- Owner: Providence Alaska Medical Center
- AMC designed the new and renovated mechanical systems to support this PAMC expansion and remodel project, which included: two new hybrid operating rooms (and new supporting mechanical penthouse), renovations to existing operating rooms and semi sterile core, remodel of the special processing and sterilization department, materials management, and other support areas.
- Additionally, AMC designed an expansion to the hospital’s existing bulk medical liquid oxygen storage tank site and equipment. The project was broken down into several “sub-projects,” each with its own phasing and interface requirements, to meet an aggressive construction schedule and maintain 24/7 hospital operational requirements. Includes: Specialized complex OR Rooms – Orthopedics, cystology, heart and hybrid.
Other Providence Projects
- Intensive Care Unit Expansion
- Surgery Expansion
- Nurse Call Replacement for the Main Campus
- Cyberknife Equipment Replacement
- Multiple Cath Labs Equipment Replacement
- Providence Imaging Center MRI Replacement
- RF Room #3 Equipment Replacement
- Nuclear Medicine Equipment Replacement
- Providence Imaging Center Mammography Equipment Improvements
- R/F X-Ray Equipment Replacement
- Epic Patient Record Project
- Master Mechanical and Electrical Autocad Records System Management